Planning a Home Renovation: Scope, Permits and Contractors
A renovation goes well or badly mostly because of decisions made before any work starts: what exactly is being done, who is doing it, what the contract says and what the building department needs to see. This page walks through that planning in order, from deciding whether to remodel at all to the week the crew arrives.
Is it time to remodel?
Start by sorting what bothers you into three groups, because each calls for a different answer:
- Things that are failing: a leaking roof, rotting window sills, a failing water heater, outdated or overloaded wiring. These are repairs and usually come first, whatever else you plan.
- Things that do not work for how you live now: a kitchen with no counter space, a missing bathroom, no main-floor bedroom for a parent, no room to work from home. This is where a remodel earns its keep.
- Things that look dated: finishes, colors and fixtures. Often fixed with paint, lighting and hardware rather than a full remodel.
If most of your list is in the second group and the fixes would mean moving walls, adding space or changing the footprint, compare the remodel with moving. Price both honestly, including the costs of selling and buying. Do not plan a project on the assumption that it will be repaid when you sell; some improvements are partly recovered at sale and many are not (see home improvements and resale value).
Step 1: write the scope
A scope is a plain description of what will be done, room by room. It is the document every quote is priced against, so the more specific it is, the more comparable the quotes will be. Include:
- What stays, what is removed and what is new.
- Layout changes, with a simple measured sketch.
- Fixtures, appliances and finishes by type and quality level, or an allowance for each if you have not chosen yet.
- What you will do or supply yourself, if anything.
- Must-haves versus nice-to-haves, so you know what to cut if the quotes come in high.
For bigger projects, an architect or designer turns the scope into drawings, and a structural engineer is needed whenever a wall, beam, joist or foundation will be removed or altered. Never assume a wall is not load-bearing because it looks thin or because someone guessed.
Step 2: permits and rules
Call or visit your local building department before you get quotes. Structural, electrical, plumbing, gas, HVAC and roofing work generally need a permit, and so do many window, deck and addition projects. A permit means the plans are reviewed and the work is inspected at set stages, which protects you as much as the next owner. Work done without a required permit can cause trouble with your insurer and when you sell, and you may be required to open finished walls so it can be inspected.
Also check zoning (setbacks, height and lot coverage for additions), HOA rules, and historic district rules if your street is in one.
Step 3: find and vet contractors
Get at least three written quotes against the same scope. For each contractor:
- Confirm the license with your state or local licensing board and ask for proof of liability insurance and workers' compensation coverage.
- Ask for recent references for similar jobs, and call them.
- Ask who will be on site each day, who pulls the permits and which trades are subcontracted. Electrical work should be done by a licensed electrician and plumbing and gas work by a licensed plumber or gas fitter.
- Be wary of anyone who knocks on your door, pressures you to sign today, asks for cash or a wire transfer, or suggests skipping the permit. The FTC's guide to avoiding home improvement scams lists more warning signs.
Do not choose on price alone. A low bid that leaves out demolition, disposal, permits or finish work will cost more by the end.
Step 4: read the contract before you sign
Insist on a written contract even where your state does not require one. It should include:
- The contractor's name, address, phone and license number.
- The full scope, drawings and specifications, or a reference to them.
- Allowances, with what happens if your choice costs more.
- Exclusions: what is not included, in writing.
- Start and completion dates and how delays are handled.
- The payment schedule, tied to completed stages rather than dates. Do not pay most of the price up front; some states limit how much a contractor may take as a deposit, so ask your state or local consumer protection office.
- A change order process: every change in writing, with price and schedule effect, signed before the work is done.
- Who is responsible for permits, inspections, cleanup and debris removal.
- Warranty terms on labor and materials.
- Lien waivers. In many US states, an unpaid subcontractor or supplier can file a lien against your home even if you paid the general contractor. Ask for lien waivers as payments are made.
Step 5: plan the schedule
Most remodels follow the same sequence, and inspections sit between the stages:
- Protection and demolition. Dust barriers, floor protection and a plan for where debris goes.
- Structural work, if any, to the engineer's design.
- Rough-in of plumbing, electrical, gas and ductwork, followed by rough inspections.
- Insulation and air sealing, sometimes with its own inspection.
- Drywall, then trim, cabinets, tile and flooring.
- Fixtures, appliances and paint.
- Final inspection, then a walkthrough with a written punch list of items to fix before the final payment.
Order long-lead items such as windows, cabinets and special-order fixtures early, because waiting on them stalls everything behind them. Decide whether you will live in the house during the work and what that means for kitchens, bathrooms, children and pets.
Safety before work starts
- Older homes: assume paint in a home built before 1978 may contain lead until tested. In the US, contractors paid to disturb that paint must be EPA lead-safe certified. Insulation, flooring, ceiling texture and pipe wrap in older homes may contain asbestos; have suspect material tested before demolition. See renovating an older home.
- Air and fumes: keep working carbon monoxide and smoke alarms throughout the work, and never run generators or gas tools indoors or in a garage.
- Your own work: if you take on part of the job, use ladders on firm, level ground with three points of contact, wear eye and hearing protection and a proper respirator for dust, and leave electrical panels, gas lines and roof work to professionals.
Put a number on it
Once the scope is written, the renovation cost estimator gives a rough first figure to test it against. It is an estimate, not a quote; only written bids for your house and your scope tell you the real price. Then build the full budget, including contingency, using how to budget a renovation.
This page explains how renovation projects generally work and is not legal advice. For questions about a specific contract, lien rights or local permit rules, consult a local attorney or your building department.